The Process

Affordable Baths Inc. completes all bathroom renovations from start to finish.  We supply all the hardware, labor, materials, etc. Our complete bathroom remodel packages are completed in a average of 10 days.  With us, there are no hidden fees, no timely delays - you can expect to have the bathroom of your dreams done professionally, on time, and on budget. 

Here is our ten day average bathroom remodeling process from start to finish:


DAY 1 - DEMO
Demolition of old Bathroom.  Remove all old Sheetrock down to the stud.  Remove old tub & Surround.  Remove old toilet and vanity.  Remove all debris.  Remove old flooring.  Install new sub floor using 1/2 Inch plywood Under Tub & Throughout Floor.  Install 1/2 inch cement board Substrate Over That to ensure floor will remain at the proper height & "Another Layer Of Protection."

DAY 2 - PLUMBING

Plumber replaces old shower body, shower valve, and drain.  He sets new Sterling Tub & Surround.  He replaces all the old stops for the hot & cold water for the vanity & toilet with new ones.
Plumbing is sub contracted through:
S.G. Racette Plumbing & Heating
MaMaster Lic# 12192 CT P1Lic#277797

DAY 3 - ELECTRICAL
Electrician roughs out for new GFCI circuit if one doesn't exist.  He installs vanity light box according to where the vanity light will be located.  He installs the ceiling fan & light combination.
Electrical is sub contracted through:
Luis Electric
Ma.Master Lic # A21310

DAY 4 & 5 - SHEETROCK / SKIMCOATING / FINISH SANDING
Installation of moisture resistant sheetrock throughout bathroom.  Tape Seams on walls & ceilings.  Skim 1st coat of joint compound. 

DAY 6 - TILE FLOORING
Tile and install new threshold.  We have to wait 24 hours in order for the tile to set before we can grout the following day. 

DAY 7 - GROUT
Grout tile and let dry.


DAY 8 - INSTALLATION OF VANITY & VANITY TOP
Installation of Vanity and Quartz Vanity Top.

DAY 9 - PLUMBING AND ELECTRICAL FINISH
Plumber sets toilet and connects cold water feed.  He makes connections for hot and cold water feeds for vanity.  He makes connection for vanity sink drain.

Electrician installs switch plates and receptacle covers.  Installs trim kit ceiling fan and light combination.  Electrician installs vanity light.

DAY 10 CARPENTRY FINISH WORK
Carpenter installs vanity and vanity top.  Carpenter installs vanity mirror.  Carpenter installs towel bar, curtain rod, cabinet hardware, and toilet paper holder.
 Carpenter installs baseboards and trim.  Carpenter goes over whole bathroom to ensure quality control and customer satisfaction.

Loading...
Previous | Next
Search   Customer Service   Contact Us
         
$9999 Complete Bathroom Remodel ›
Learn Our Process ›
Handicap Accessible Bathrooms ›
Bathroom Upgrades ›
Testimonials ›
Gallery ›
 

Finance Your Remodel ›
Contact Customer Service ›
Visit Our Showroom ›
Request a Consultation ›

 

 

  Affordable Baths Inc
Showroom Address:
357 Cottage St. Springfield, MA
Get Directions ›

Offices:
MA: 413-209-3797
CT: 860-814-4003
Worcester: 508-615-5426


Email: info@affordablebaths.net